The new Grocery Framework will commence on 3rd September 2012.
Below is the current timetable (using an OJEU Restricted Procedure)
(Dates may be subject to change but will remain within OJEU requirements)
5th March - TPL will send contract notice to OJEU
17th April - PQQ closing date
11th May - Appraisal of returned PQQ Document
14th May - Invite tenders from short-listed suppliers
15th June - ITT closing date
18th & 19th July - Evaluation & Award Meeting
31st July - Contract Final Award
2nd August - Post Tender Mobilisation Meeting with Successfull suppliers